HBS Marineview, Kalbadevi

Lapsed

by HBS Seaview Pvt Ltd · Kalbadevi, Mumbai 400002 · Map

Launched
Aug 20178 yrs 4 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
32 of 7742%
Buildings
10.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
37
3 BHK
40
Total units
77
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%32
0%0%0%–
0%0%0%–
0%0%0%32

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

HBS Marineview by HBS Seaview Pvt Ltd is a 77-unit project in Kalbadevi, Mumbai 400002, launched in August 2017; its MahaRERA registration has lapsed. 32 units booked out of total 77 units. Work on the concrete structure (RCC) has not started.

Read full summary

HBS Marineview is a project by HBS Seaview Pvt Ltd in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900009287. It was launched in August 2017. It has 77 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.

32 units booked out of total 77 units (42%).