Lb One, Worli

Lapsed

by Lokhandwala Infrastructure Private Limited · Worli, Mumbai 400018 · Map

Launched
Aug 20178 yrs 4 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
11 acre
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
1
3 BHK
73
5+ BHK
14
Total units
88
Buildings
1
Land
1 acre
Phases
1
MahaRERA complaints
6

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%–
0%0%0%–
0%0%0%–
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Lb One by Lokhandwala Infrastructure Private Limited is an 88-unit BMC-sanctioned project in Worli, Mumbai 400018, launched in August 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Lb One is a BMC-sanctioned project by Lokhandwala Infrastructure Private Limited in Worli, Mumbai 400018, registered with MahaRERA as P51900009787. It was launched in August 2017. It has 88 units in 1 building, with 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation not started, structure (RCC) not started, final finishes not started.