- Launched
- Aug 20172 yrs originally promised
- Possession (MahaRERA)
- Dec 2024Extended by 5 yrs 4 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 31 of 3491%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 34
- Total units
- 34
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 31 | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | – | |
| 100% | 100% | 10% | 31 |
"–" means MahaRERA shows no figure for that update.
About this project
Fortune Vue C Wing by Alf Developers is a 34-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017; its MahaRERA registration has lapsed. 31 units booked out of total 34 units. The concrete structure (RCC) is complete.
Read full summary
Fortune Vue C Wing is a BMC-sanctioned project by Alf Developers in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900010150. It was launched in August 2017. It has 34 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2024, after an extension of 5 years 4 months from the original August 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.
31 units booked out of total 34 units (91%).