Building no 4 on portion of CTS no 442 part 444 part 447 part and 625 part, Sewri

Lapsed

by East And West Builders · Sewri, Mumbai 400015 · Map

Launched
Aug 20176 yrs 4 mths promised
Possession (MahaRERA)
Dec 2023Not extendedWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
–
Buildings
13.8 acres
MahaRERA complaints
12Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
324
3 BHK
172
Total units
496
Buildings
1
Land
3.8 acres
Phases
1
MahaRERA complaints
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation86%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 86%Dec 2025: Excavation 86%Jul 2026: Excavation 86%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 86%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
86%0%0%–
86%0%0%–
86%0%0%179

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Building no 4 on portion of CTS no 442 part 444 part 447 part and 625 part by East And West Builders is a 496-unit project in Sewri, Mumbai 400015, launched in August 2017; its MahaRERA registration has lapsed. Work on the concrete structure (RCC) has not started.

Read full summary

Building no 4 on portion of CTS no 442 part 444 part 447 part and 625 part is a project by East And West Builders in Sewri, Mumbai 400015, registered with MahaRERA as P51900011167. It was launched in August 2017. It has 496 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation 86% complete, structure (RCC) not started, final finishes not started.