Nathani Heights Sale, Mahalaxmi

by Nathani Parekh Constructions Private Limited · Mahalaxmi, Mumbai 400011 · Map

Launched
Aug 20178 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr
Concrete structure
92%Mid-construction
Booked
740 of 81591% · 571 in Jul 2026
Buildings
11.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
53
4 BHK
67
Other units
695
Total units
815
Buildings
1
Land
1.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 86%Dec 2025: Concrete structure (RCC) 88%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 66%Dec 2025: Final finishes 66%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 92%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%75%740
100%92%75%571
100%88%66%571
100%86%66%515

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400011

Projects with 60–250 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400011
MeasureThis projectSimilar projects
Launch to possession (as first promised)8 yrs 4 mths5 yrs 4 mths
Possession date extendedBy 1 yr1 of 3
Possession date (MahaRERA)Dec 2026Jul 2024
Concrete structure (RCC)92%54%
Units booked91%86%
MahaRERA complaints (filed by or against the builder)01

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Nathani Heights Sale by Nathani Parekh Constructions Private Limited is an 815-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017 with possession due in December 2026. 740 units booked out of total 815 units. The concrete structure (RCC) is 92% complete.

Read full summary

Nathani Heights Sale is a BMC-sanctioned project by Nathani Parekh Constructions Private Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900011250. It was launched in August 2017. It has 815 units in 1 building: 120 homes (3 and 4 BHK) and 695 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) 92% complete, final finishes 75% complete.

740 units booked out of total 815 units (91%). Since the July 2026 update, 169 more units have been booked.