Ibrahim Residency, Mahalaxmi

Lapsed

by Y H Assoicates · Mahalaxmi, Mumbai 400011 · Map

Launched
Aug 20176 yrs 11 mths promised
Possession (MahaRERA)
Jul 2024Not extendedWhat does Lapsed mean?
Concrete structure
67%Mid-construction
Booked (free sale)
38 of 3997% · 52 rehab units
Buildings
30.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale38 booked out of 39 units

Rehab52 units for existing members

Land-owner share8 units, not for sale

Total 99 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
99
Total units
99
Buildings
3
Land
0.2 acres
Phases
1
MahaRERA complaints
1
Free-sale units
39
Rehab units
52
Land-owner share (not for sale)
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation67%
Concrete structure (slabs)67%
Finishes, lifts and services65%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 67%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Dec 2024: Concrete structure (RCC) 67%Dec 2025: Concrete structure (RCC) 67%Jul 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 65%Dec 2025: Final finishes 65%Jul 2026: Final finishes 65%Excavation 67%Concrete structure (RCC) 67%Final finishes 65%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%67%65%38
67%67%65%–
67%67%65%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400011

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400011
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 11 mths5 yrs 4 mths
Possession date extendedNo2 of 3
Possession date (MahaRERA)Jul 2024Dec 2026
Concrete structure (RCC)67%54%
Units booked (free sale)97%86%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Ibrahim Residency by Y H Assoicates is a 99-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2017; its MahaRERA registration has lapsed. 38 units booked out of 39 units for sale. The concrete structure (RCC) is 67% complete.

Read full summary

Ibrahim Residency is a BMC-sanctioned project by Y H Assoicates in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900007987. It was launched in August 2017. It has 99 units in 3 buildings, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 99 units, 39 are for sale, 52 are rehab units for existing members and 8 are the land-owner's share, not for sale.

Possession was due in July 2024. That date has passed and no extension has been recorded. Construction: excavation 67% complete, structure (RCC) 67% complete, final finishes 65% complete.

38 units booked out of 39 units for sale (97%).