Skip to main content

Raman Tara Heights, Mandvi

Lapsed

by Surendra Mody And Others · Mandvi, Mumbai 400003 · Map

Launched
Aug 20174 mths promised
Possession (MahaRERA)
Dec 2017Not extendedWhat does Lapsed mean?
Concrete structure
50%Mid-construction
Booked
–
Buildings
1
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
22
Total units
22
Buildings
1
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)50%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 100%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 50%Concrete structure (RCC) 50%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%50%50%–
50%50%50%–
100%100%100%14

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Raman Tara Heights by Surendra Mody And Others is a 22-unit project in Mandvi, Mumbai 400003, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 50% complete.

Read full summary

Raman Tara Heights is a project by Surendra Mody And Others in Mandvi, Mumbai 400003, registered with MahaRERA as P51900011462. It was launched in August 2017. It has 22 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2017. That date has passed and no extension has been recorded. Construction: excavation 50% complete, structure (RCC) 50% complete, final finishes 50% complete.