Marina Bay Worli Sea Face, Worli
Ready to moveLapsed
by Saumya Buildcon Pvt Ltd · Worli, Mumbai 400030 · Map
- Launched
- Aug 20175 yrs 5 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 3 yrs 8 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 103 of 27537%
- Buildings
- 11.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 18
- 3 BHK
- 54
- 4 BHK
- 52
- Other units
- 151
- Total units
- 275
- Buildings
- 1
- Land
- 1.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 103 | |
| 100% | 100% | 100% | 103 | |
| 100% | 93% | 40% | 98 | |
| 100% | 56% | 10% | 78 |
"–" means MahaRERA shows no figure for that update.
About this project
Marina Bay Worli Sea Face by Saumya Buildcon Pvt Ltd is a 275-unit BMC-sanctioned project in Worli, Mumbai 400030, launched in August 2017; its MahaRERA registration has lapsed. 103 units booked out of total 275 units. The concrete structure (RCC) is complete.
Read full summary
Marina Bay Worli Sea Face is a BMC-sanctioned project by Saumya Buildcon Pvt Ltd in Worli, Mumbai 400030, registered with MahaRERA as P51900011592. It was launched in August 2017. It has 275 units in 1 building: 124 homes (1 RK, 3 BHK and 4 BHK) and 151 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in September 2026, after an extension of 3 years 8 months from the original January 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
103 units booked out of total 275 units (37%).