Al Mehdi Heights, Chinchbunder

Lapsed

by Al Haadi Developers · Chinchbunder, Mumbai 400009 · Map

Launched
Aug 20172 yrs 8 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 3 yrs 8 mthsWhat does Lapsed mean?
Concrete structure
87%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
270
2 BHK
10
4 BHK
1
Total units
281
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)87%
Finishes, lifts and services45%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 87%Jul 2026: Concrete structure (RCC) 87%Dec 2024: Final finishes 45%Dec 2025: Final finishes 45%Jul 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 87%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%87%45%–
100%87%45%–
100%87%45%170

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Al Mehdi Heights by Al Haadi Developers is a 281-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 87% complete.

Read full summary

Al Mehdi Heights is a BMC-sanctioned project by Al Haadi Developers in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900011681. It was launched in August 2017. It has 281 units in 1 building, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2023, after an extension of 3 years 8 months from the original April 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 87% complete, final finishes 45% complete.