- Launched
- Aug 20172 yrs 8 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 3 yrs 8 mthsWhat does Lapsed mean?
- Concrete structure
- 87%Mid-construction
- Booked
- –
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 270
- 2 BHK
- 10
- 4 BHK
- 1
- Total units
- 281
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 45% | – | |
| 100% | 87% | 45% | – | |
| 100% | 87% | 45% | 170 |
"–" means MahaRERA shows no figure for that update.
About this project
Al Mehdi Heights by Al Haadi Developers is a 281-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 87% complete.
Read full summary
Al Mehdi Heights is a BMC-sanctioned project by Al Haadi Developers in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900011681. It was launched in August 2017. It has 281 units in 1 building, with 1, 2 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023, after an extension of 3 years 8 months from the original April 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 87% complete, final finishes 45% complete.