- Launched
- Sep 20173 yrs 9 mths originally promised
- Possession (MahaRERA)
- Jun 2022Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 87%Mid-construction
- Booked
- 71 of 28425%
- Buildings
- 21.6 acres
- MahaRERA complaints
- 6Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 104
- 5+ BHK
- 132
- Other units
- 48
- Total units
- 284
- Buildings
- 2
- Land
- 1.6 acres
- Phases
- 1
- MahaRERA complaints
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 73% | 71 | |
| 100% | 87% | 73% | – | |
| 100% | 87% | 73% | – | |
| 100% | 87% | 73% | 71 |
"–" means MahaRERA shows no figure for that update.
About this project
Three Sixty West by Oasis Realty is a 284-unit project in Prabhadevi, Mumbai 400025, launched in September 2017; its MahaRERA registration has lapsed. 71 units booked out of total 284 units. The concrete structure (RCC) is 87% complete.
Read full summary
Three Sixty West is a project by Oasis Realty in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900012115. It was launched in September 2017. It has 284 units in 2 buildings: 236 homes (4 and 5+ BHK) and 48 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2022, after an extension of 1 year from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 87% complete, final finishes 73% complete.
71 units booked out of total 284 units (25%).