Om Gopal - Floor 3 to 9, Dadar West
Ready to moveLapsed
by Omkar Realtors and Developers Private Limited · Dadar West, Mumbai 400028 · Map
- Launched
- Sep 20173 yrs 3 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 5 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- –
- Buildings
- 10.6 acres
- MahaRERA complaints
- 7Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 103
- Total units
- 103
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | 89 |
"–" means MahaRERA shows no figure for that update.
About this project
Om Gopal - Floor 3 to 9 by Omkar Realtors and Developers Private Limited is a 103-unit project in Dadar West, Mumbai 400028, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.
Read full summary
Om Gopal - Floor 3 to 9 is a project by Omkar Realtors and Developers Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900012360. It was launched in September 2017. It has 103 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 5 years 6 months from the original December 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
Omkar's track record in Mumbai
MahaRERA projects registered 2017–2017 in Mumbai
| Projects registered with MahaRERA | 4 |
|---|---|
| Total units across these projects | 424 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 0 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Omkar projects | 27 (3 of 4 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.