- Launched
- Sep 20172 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 8 yrs
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 27 of 3773% · 35 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale27 booked out of 37 units
Rehab35 units for existing members
Total 72 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 67
- Other units
- 5
- Total units
- 72
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 37
- Rehab units
- 35
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 27 | |
| 100% | 100% | 95% | 27 | |
| 100% | 78% | 90% | – | |
| 100% | 78% | 90% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400010
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 3 mths | 2 yrs 1 mth |
| Possession date extended | By 8 yrs | 2 of 3 |
| Possession date (MahaRERA) | Dec 2027 | Apr 2020 |
| Concrete structure (RCC) | 100% | 73% |
| MahaRERA complaints (filed by or against the builder) | 2 | 0 |
The 3 projects
- Belvedre Hills, Mazgaon
- Halima Residency, Mazgaon
- Nakhwa Heritage, Mazgaon
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Belvedre Hills | August 2017 | April 2020 | 100% | – |
| Halima Residency | August 2017 | December 2027 | 73% | 0 units booked out of total 35 units |
| Nakhwa Heritage | November 2017 | December 2019 | 25% | – |
About this project
Saif towers by Mustanshir Saifuddin Merchant is a 72-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in September 2017 with possession due in December 2027. 27 units booked out of 37 units for sale. The concrete structure (RCC) is complete.
Read full summary
Saif towers is a BMC-sanctioned project by Mustanshir Saifuddin Merchant in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900012891. It was launched in September 2017. It has 72 units in 1 building: 67 homes (1 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 37 are for sale and 35 are rehab units for existing members.
Its registered possession date is December 2027, extended by 8 years from the original December 2019. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
27 units booked out of 37 units for sale (73%).