Halima Residency, Mazgaon

by Dhunjibhoy Ice Factory Pvt Ltd · Mazgaon, Mumbai 400010 · Map

Launched
Aug 20175 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 4 yrs 5 mths
Concrete structure
73%Mid-construction
Booked
0 of 350%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
9
2 BHK
26
Total units
35
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)73%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 55%Jul 2026: Concrete structure (RCC) 64%Oct 2026: Concrete structure (RCC) 73%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 55%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 73%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%73%70%0
100%64%55%0
100%55%0%0
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400010

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400010
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 11 mths2 yrs 3 mths
Possession date extendedBy 4 yrs 5 mths3 of 5
Possession date (MahaRERA)Dec 2027Dec 2022
Concrete structure (RCC)73%100%
Units booked0%73%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Halima Residency by Dhunjibhoy Ice Factory Pvt Ltd is a 35-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in August 2017 with possession due in December 2027. 0 units booked out of total 35 units. The concrete structure (RCC) is 73% complete.

Read full summary

Halima Residency is a BMC-sanctioned project by Dhunjibhoy Ice Factory Pvt Ltd in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900006273. It was launched in August 2017. It has 35 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 4 years 5 months from the original July 2023. Construction: excavation complete, structure (RCC) 73% complete, final finishes 70% complete.

0 units booked out of total 35 units (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 64% to 73%.