La Verna, Kalbadevi

Lapsed

by M/s Qaswa Enterprises · Kalbadevi, Mumbai 400002 · Map

Launched
Oct 20171 yr 2 mths originally promised
Possession (MahaRERA)
Dec 2019Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
30 of 3977%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
39
Total units
39
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services30%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 30%Dec 2025: Final finishes 15%Jul 2026: Final finishes 15%Oct 2026: Final finishes 30%Excavation 100%Concrete structure (RCC) 100%Final finishes 30%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%30%30
50%50%15%–
50%50%15%–
100%100%30%30

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

La Verna by M/s Qaswa Enterprises is a 39-unit project in Kalbadevi, Mumbai 400002, launched in October 2017; its MahaRERA registration has lapsed. 30 units booked out of total 39 units. The concrete structure (RCC) is complete.

Read full summary

La Verna is a project by M/s Qaswa Enterprises in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900013447. It was launched in October 2017. It has 39 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2019, after an extension of 1 year from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.

30 units booked out of total 39 units (77%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 100%.