Bhavya Enclave, Khar West
Lapsed
by Bhavya Infrastructures (India) Private Limited · Khar West, Mumbai 400052 · Map
- Launched
- Oct 20171 yr 8 mths promised
- Possession (MahaRERA)
- Jun 2019Not extendedWhat does Lapsed mean?
- Concrete structure
- 60%Mid-construction
- Booked
- 27 of 5252%
- Buildings
- 10.6 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 52
- Total units
- 52
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 85% | 60% | 0% | 27 | |
| 85% | 60% | 0% | – | |
| 85% | 60% | 0% | – | |
| 85% | 60% | 0% | 27 |
"–" means MahaRERA shows no figure for that update.
About this project
Bhavya Enclave by Bhavya Infrastructures (India) Private Limited is a 52-unit project in Khar West, Mumbai 400052, launched in October 2017; its MahaRERA registration has lapsed. 27 units booked out of total 52 units. The concrete structure (RCC) is 60% complete.
Read full summary
Bhavya Enclave is a project by Bhavya Infrastructures (India) Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51900013855. It was launched in October 2017. It has 52 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2019. That date has passed and no extension has been recorded. Construction: excavation 85% complete, structure (RCC) 60% complete, final finishes not started.
27 units booked out of total 52 units (52%).