Saqlainia Heights, Chinchbunder

Lapsed

by Mohdyusuf Usmangani Sherawala · Chinchbunder, Mumbai 400009 · Map

Launched
Mar 20186 mths originally promised
Possession (MahaRERA)
Sep 2025Extended by 7 yrsWhat does Lapsed mean?
Concrete structure
10%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
16
2 BHK
28
Other units
14
Total units
58
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)10%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 10%Dec 2024: Final finishes 100%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 50%Final finishes 50%Concrete structure (RCC) 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%10%50%–
50%10%50%–
100%20%100%58

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Saqlainia Heights by Mohdyusuf Usmangani Sherawala is a 58-unit project in Chinchbunder, Mumbai 400009, launched in March 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is 10% complete.

Read full summary

Saqlainia Heights is a project by Mohdyusuf Usmangani Sherawala in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900015499. It was launched in March 2018. It has 58 units in 1 building: 44 homes (1 and 2 BHK) and 14 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2025, after an extension of 7 years from the original September 2018. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) 10% complete, final finishes 50% complete.