Arihant Heritage - Old Laxmi Building, Parel
Ready to moveLapsed
by Arihant Devlopers · Parel, Mumbai 400012 · Map
- Launched
- Apr 20183 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 7 yrs 5 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 52 of 6481% · 9 in Jul 2026
- Buildings
- 10.1 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 36
- 2 BHK
- 28
- Total units
- 64
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 52 | |
| 100% | 100% | 0% | 9 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 52 |
"–" means MahaRERA shows no figure for that update.
About this project
Arihant Heritage - Old Laxmi Building by Arihant Devlopers is a 64-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in April 2018; its MahaRERA registration has lapsed. 52 units booked out of total 64 units. The concrete structure (RCC) is complete.
Read full summary
Arihant Heritage - Old Laxmi Building is a BMC-sanctioned project by Arihant Devlopers in Parel, Mumbai 400012, registered with MahaRERA as P51900015921. It was launched in April 2018. It has 64 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2025, after an extension of 7 years 5 months from the original July 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
52 units booked out of total 64 units (81%). Since the July 2026 update, 43 more units have been booked and the possession date has moved from March 2024 to December 2025.