Siddhi Yog, Mahim

Lapsed

by Siddhitech Developers Private Limited · Mahim, Mumbai 400016 · Map

Launched
Jul 20185 yrs 5 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 2 yrsWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
16 of 16100%
Buildings
10.2 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
8
3 BHK
8
Total units
16
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 84%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 85%Dec 2025: Final finishes 85%Jul 2026: Final finishes 85%Oct 2026: Final finishes 85%Excavation 100%Final finishes 85%Concrete structure (RCC) 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%85%16
100%80%85%16
100%80%85%16
100%84%85%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Siddhi Yog by Siddhitech Developers Private Limited is a 16-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in July 2018; its MahaRERA registration has lapsed. 16 units booked out of total 16 units. The concrete structure (RCC) is 80% complete.

Read full summary

Siddhi Yog is a BMC-sanctioned project by Siddhitech Developers Private Limited in Mahim, Mumbai 400016, registered with MahaRERA as P51900017229. It was launched in July 2018. It has 16 units in 1 building, with 1 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 85% complete.

16 units booked out of total 16 units (100%).