- Launched
- Aug 20184 yrs 10 mths originally promised
- Possession (MahaRERA)
- Jun 2024Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 45%Mid-construction
- Booked
- 8 of 5515%
- Buildings
- 10.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 4 BHK
- 50
- 5+ BHK
- 5
- Total units
- 55
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 45% | 0% | 8 | |
| 100% | 45% | 0% | – | |
| 100% | 45% | 0% | – | |
| 100% | 45% | 0% | 8 |
"–" means MahaRERA shows no figure for that update.
About this project
Sumer Trinity Vertical Phase-I by Sumer Builders is a 55-unit project in Prabhadevi, Mumbai 400025, launched in August 2018; its MahaRERA registration has lapsed. 8 units booked out of total 55 units. The concrete structure (RCC) is 45% complete.
Read full summary
Sumer Trinity Vertical Phase-I is a project by Sumer Builders in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900017371. It was launched in August 2018. It has 55 units in 1 building, with 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2024, after an extension of 1 year from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.
8 units booked out of total 55 units (15%).