Sumer Trinity Vertical Phase-I, Prabhadevi

Lapsed

by Sumer Builders · Prabhadevi, Mumbai 400025 · Map

Launched
Aug 20184 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
45%Mid-construction
Booked
8 of 5515%
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
50
5+ BHK
5
Total units
55
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 45%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%45%0%8
100%45%0%–
100%45%0%–
100%45%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sumer Trinity Vertical Phase-I by Sumer Builders is a 55-unit project in Prabhadevi, Mumbai 400025, launched in August 2018; its MahaRERA registration has lapsed. 8 units booked out of total 55 units. The concrete structure (RCC) is 45% complete.

Read full summary

Sumer Trinity Vertical Phase-I is a project by Sumer Builders in Prabhadevi, Mumbai 400025, registered with MahaRERA as P51900017371. It was launched in August 2018. It has 55 units in 1 building, with 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2024, after an extension of 1 year from the original June 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 45% complete, final finishes not started.

8 units booked out of total 55 units (15%).