- Launched
- Oct 20184 yrs 5 mths originally promised
- Possession (MahaRERA)
- Sep 2025Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 12 of 1580% · 16 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 15 units
Rehab16 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 8
- 2 BHK
- 9
- 3 BHK
- 10
- 4 BHK
- 2
- Other units
- 2
- Total units
- 31
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 15
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 80% | 12 | |
| 100% | 100% | 80% | 12 | |
| 100% | 100% | 80% | 12 | |
| 100% | 100% | 50% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shivji Krupa by Bharatchandra Jeram Thakker is a 31-unit BMC-sanctioned project in Matunga, Mumbai 400019, launched in October 2018; its MahaRERA registration has lapsed. 12 units booked out of 15 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shivji Krupa is a BMC-sanctioned project by Bharatchandra Jeram Thakker in Matunga, Mumbai 400019, registered with MahaRERA as P51900018231. It was launched in October 2018. It has 31 units in 1 building: 29 homes (1, 2, 3 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 31 units, 15 are for sale and 16 are rehab units for existing members.
Possession was due in September 2025, after an extension of 2 years 6 months from the original March 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 80% complete.
12 units booked out of 15 units for sale (80%).