Skip to main content

CCIL Bhavan, Dadar West

Ready to move

by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map

Launched
Aug 20195 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 3 yrs
Concrete structure
100%Ready to move
Booked
3 of 3100%
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
3
Total units
3
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%3
100%0%0%3
100%0%0%–
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

CCIL Bhavan by Suraj Estate Developers Ltd is a 3-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in August 2019 with possession due in December 2027. 3 units booked out of total 3 units. The concrete structure (RCC) is complete.

Read full summary

CCIL Bhavan is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as P51900021953. It was launched in August 2019. It has 3 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 3 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

3 units booked out of total 3 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from June 2026 to December 2027.

Suraj Estate's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA17
Total units across these projects1,217
Completed without extending the possession date0
Completed after an extension4
Lapsed3
Under construction10
Possession date extended on the builder's application10
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Suraj Estate projects11 (6 of 17 projects)

See all Suraj Estate projects →