Earth Anand, Chinchbunder

Lapsed

by M/s. Earth Graphics · Chinchbunder, Mumbai 400009 · Map

Launched
Aug 20194 yrs 4 mths originally promised
Possession (MahaRERA)
May 2025Extended by 1 yr 5 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
16 of 5330%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
53
Total units
53
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%16
100%100%50%–
100%100%50%–
100%100%50%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Earth Anand by M/s. Earth Graphics is a 53-unit BMC-sanctioned project in Chinchbunder, Mumbai 400009, launched in August 2019; its MahaRERA registration has lapsed. 16 units booked out of total 53 units. The concrete structure (RCC) is complete.

Read full summary

Earth Anand is a BMC-sanctioned project by M/s. Earth Graphics in Chinchbunder, Mumbai 400009, registered with MahaRERA as P51900021985. It was launched in August 2019. It has 53 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in May 2025, after an extension of 1 year 5 months from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

16 units booked out of total 53 units (30%).