Vanu Heights, Wadala East

Ready to moveLapsed

by Vanu Developers Private Limited · Wadala East, Mumbai 400037 · Map

Launched
Dec 20196 yrs originally promised
Possession (MahaRERA)
Apr 2026Extended by 4 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
19 of 6032%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
45
2 BHK
15
Total units
60
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 95%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%19
100%100%95%19
100%100%25%15
100%100%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vanu Heights by Vanu Developers Private Limited is a 60-unit SRA-sanctioned project in Wadala East, Mumbai 400037, launched in December 2019; its MahaRERA registration has lapsed. 19 units booked out of total 60 units. The concrete structure (RCC) is complete.

Read full summary

Vanu Heights is an SRA-sanctioned project by Vanu Developers Private Limited in Wadala East, Mumbai 400037, registered with MahaRERA as P51900023322. It was launched in December 2019. It has 60 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in April 2026, after an extension of 4 months from the original December 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

19 units booked out of total 60 units (32%).