Necklace View, Kalbadevi

Lapsed

by Aasma Infra-Con LLP · Kalbadevi, Mumbai 400002 · Map

Launched
Jan 20203 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
16
Total units
16
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%–
100%100%10%–
100%100%10%–
100%100%10%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Necklace View by Aasma Infra-Con LLP is a 16-unit project in Kalbadevi, Mumbai 400002, launched in January 2020; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Necklace View is a project by Aasma Infra-Con LLP in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900023891. It was launched in January 2020. It has 16 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.