Kundan Apt, Jogeshwari East

Lapsed

by Tanna Developers · Jogeshwari East, Mumbai 400060 · Map

Launched
Aug 20201 yr 10 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 3 yrs 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
7 of 1354%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
11
2 BHK
2
Total units
13
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%7
100%100%0%–
100%100%0%–
100%100%0%7

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Kundan Apt by Tanna Developers is a 13-unit project in Jogeshwari East, Mumbai 400060, launched in August 2020; its MahaRERA registration has lapsed. 7 units booked out of total 13 units. The concrete structure (RCC) is complete.

Read full summary

Kundan Apt is a project by Tanna Developers in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51900026193. It was launched in August 2020. It has 13 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 3 years 6 months from the original June 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

7 units booked out of total 13 units (54%).