Bhavya Elite, Wadala East
Ready to moveLapsed
by Newlook Constructions Pvt Ltd · Wadala East, Mumbai 400037 · Map
- Launched
- Jan 20214 yrs 5 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 206 of 30568% · 98 in Jul 2026
- Buildings
- 11 acre
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 78
- 2 BHK
- 227
- Total units
- 305
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 206 | |
| 100% | 98% | 70% | 98 | |
| 100% | 98% | 70% | 98 | |
| 100% | 98% | 70% | 56 |
"–" means MahaRERA shows no figure for that update.
About this project
Bhavya Elite by Newlook Constructions Pvt Ltd is a 305-unit SRA-sanctioned project in Wadala East, Mumbai 400037, launched in January 2021; its MahaRERA registration has lapsed. 206 units booked out of total 305 units. The concrete structure (RCC) is complete.
Read full summary
Bhavya Elite is an SRA-sanctioned project by Newlook Constructions Pvt Ltd in Wadala East, Mumbai 400037, registered with MahaRERA as P51900027909. It was launched in January 2021. It has 305 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
206 units booked out of total 305 units (68%). Since the July 2026 update, 108 more units have been booked and the reported concrete structure (RCC) has gone from 98% to 100%.