- Launched
- Mar 20215 yrs 2 mths promised
- Possession (MahaRERA)
- May 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 23 of 23100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale23 booked out of 23 units
Land-owner share35 units, not for sale
Total 58 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 57
- 2 BHK
- 1
- Total units
- 58
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 23
- Land-owner share (not for sale)
- 35
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 25% | 23 | |
| 100% | 100% | 25% | 23 | |
| 100% | 100% | 25% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Ali Tower by Alamdar Infrastructure Pvt Ltd is a 58-unit BMC-sanctioned project in Mandvi, Mumbai 400003, launched in March 2021; its MahaRERA registration has lapsed. 23 units booked out of 23 units for sale. The concrete structure (RCC) is complete.
Read full summary
Ali Tower is a BMC-sanctioned project by Alamdar Infrastructure Pvt Ltd in Mandvi, Mumbai 400003, registered with MahaRERA as P51900028809. It was launched in March 2021. It has 58 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 58 units, 23 are for sale and 35 are the land-owner's share, not for sale.
Possession was due in May 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.
23 units booked out of 23 units for sale (100%).