- Launched
- May 20214 yrs 4 mths originally promised
- Possession (MahaRERA)
- Sep 2026Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 82%Mid-construction
- Booked (free sale)
- 24 of 3177% · 30 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 7Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 31 units
Rehab30 units for existing members
Total 61 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 48
- 2 BHK
- 3
- Other units
- 8
- Total units
- 61
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 7
- Free-sale units
- 31
- Rehab units
- 30
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 82% | 5% | 24 | |
| 100% | 82% | 5% | 24 | |
| 100% | 82% | 5% | 24 | |
| 100% | 63% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Inspire by R K Constructions is a 61-unit BMC-sanctioned project in Parel, Mumbai 400012, launched in May 2021; its MahaRERA registration has lapsed. 24 units booked out of 31 units for sale. The concrete structure (RCC) is 82% complete.
Read full summary
Inspire is a BMC-sanctioned project by R K Constructions in Parel, Mumbai 400012, registered with MahaRERA as P51900029171. It was launched in May 2021. It has 61 units in 1 building: 53 homes (1 RK, 1 BHK and 2 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 61 units, 31 are for sale and 30 are rehab units for existing members.
Possession was due in September 2026, after an extension of 1 year from the original September 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 82% complete, final finishes 5% complete.
24 units booked out of 31 units for sale (77%).