Skip to main content

Vitalis, Mahim

by Suraj Estate Developers Ltd · Mahim, Mumbai 400016 · Map

Launched
Oct 20215 yrs 2 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
70%Mid-construction
Booked (free sale)
86 of 8799% · 81 rehab units
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale86 booked out of 87 units

Rehab81 units for existing members

Land-owner share16 units, not for sale

Total 184 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
84
2 BHK
80
3 BHK
2
4 BHK
2
Other units
16
Total units
184
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0
Free-sale units
87
Rehab units
81
Land-owner share (not for sale)
16
Reserved units
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)70%
Finishes, lifts and services2%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 16%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 2%Oct 2026: Final finishes 2%Excavation 100%Concrete structure (RCC) 70%Final finishes 2%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%70%2%86
100%16%2%86
100%0%0%85
100%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vitalis by Suraj Estate Developers Ltd is a 184-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in October 2021 with possession due in December 2026. 86 units booked out of 87 units for sale. The concrete structure (RCC) is 70% complete.

Read full summary

Vitalis is a BMC-sanctioned project by Suraj Estate Developers Ltd in Mahim, Mumbai 400016, registered with MahaRERA as P51900031447. It was launched in October 2021. It has 184 units in 1 building: 168 homes (1, 2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 184 units, 87 are for sale, 81 are rehab units for existing members and 16 are the land-owner's share, not for sale.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes 2% complete.

86 units booked out of 87 units for sale (99%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 16% to 70%.

Suraj Estate's track record in Mumbai

MahaRERA projects registered 2017–2025 in Mumbai

Projects registered with MahaRERA17
Total units across these projects1,217
Completed without extending the possession date0
Completed after an extension4
Lapsed3
Under construction10
Possession date extended on the builder's application10
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Suraj Estate projects11 (6 of 17 projects)

See all Suraj Estate projects →