Vitalis, Mahim
by Suraj Estate Developers Ltd · Mahim, Mumbai 400016 · Map
- Launched
- Oct 20215 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 86 of 8799% · 81 rehab units
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale86 booked out of 87 units
Rehab81 units for existing members
Land-owner share16 units, not for sale
Total 184 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 84
- 2 BHK
- 80
- 3 BHK
- 2
- 4 BHK
- 2
- Other units
- 16
- Total units
- 184
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 87
- Rehab units
- 81
- Land-owner share (not for sale)
- 16
- Reserved units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 2% | 86 | |
| 100% | 16% | 2% | 86 | |
| 100% | 0% | 0% | 85 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Vitalis by Suraj Estate Developers Ltd is a 184-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in October 2021 with possession due in December 2026. 86 units booked out of 87 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
Vitalis is a BMC-sanctioned project by Suraj Estate Developers Ltd in Mahim, Mumbai 400016, registered with MahaRERA as P51900031447. It was launched in October 2021. It has 184 units in 1 building: 168 homes (1, 2, 3 and 4 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 184 units, 87 are for sale, 81 are rehab units for existing members and 16 are the land-owner's share, not for sale.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes 2% complete.
86 units booked out of 87 units for sale (99%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 16% to 70%.
Suraj Estate's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 1,217 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 4 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Suraj Estate projects | 11 (6 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.