22Avenue, Sion

Ready to moveLapsed

by Sahaj Infra & Project LLP · Sion, Mumbai 400022 · Map

Launched
Oct 20214 yrs 2 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
10 of 1471% · 26 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale10 booked out of 14 units

Rehab26 units for existing members

Land-owner share4 units, not for sale

Total 44 units. Rehab and land-owner units are not for sale.

Project facts

1 RK
1
1 BHK
16
2 BHK
3
3 BHK
15
4 BHK
6
Other units
3
Total units
44
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
14
Rehab units
26
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 99%Jul 2026: Final finishes 99%Oct 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%10
100%100%99%10
100%100%99%9
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

22Avenue by Sahaj Infra & Project LLP is a 44-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in October 2021; its MahaRERA registration has lapsed. 10 units booked out of 14 units for sale. The concrete structure (RCC) is complete.

Read full summary

22Avenue is a BMC-sanctioned project by Sahaj Infra & Project LLP in Sion, Mumbai 400022, registered with MahaRERA as P51900031593. It was launched in October 2021. It has 44 units in 1 building: 41 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 44 units, 14 are for sale, 26 are rehab units for existing members and 4 are the land-owner's share, not for sale.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

10 units booked out of 14 units for sale (71%).