- Launched
- Oct 20214 yrs 2 mths promised
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 10 of 1471% · 26 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 14 units
Rehab26 units for existing members
Land-owner share4 units, not for sale
Total 44 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 16
- 2 BHK
- 3
- 3 BHK
- 15
- 4 BHK
- 6
- Other units
- 3
- Total units
- 44
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Rehab units
- 26
- Land-owner share (not for sale)
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 10 | |
| 100% | 100% | 99% | 10 | |
| 100% | 100% | 99% | 9 | |
| 80% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
22Avenue by Sahaj Infra & Project LLP is a 44-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in October 2021; its MahaRERA registration has lapsed. 10 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
22Avenue is a BMC-sanctioned project by Sahaj Infra & Project LLP in Sion, Mumbai 400022, registered with MahaRERA as P51900031593. It was launched in October 2021. It has 44 units in 1 building: 41 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 44 units, 14 are for sale, 26 are rehab units for existing members and 4 are the land-owner's share, not for sale.
Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
10 units booked out of 14 units for sale (71%).