by Sudhir Vasant Mayekar · Dadar West, Mumbai 400028 · Map

Launched
Nov 20213 yrs 1 mth originally promised
Possession (MahaRERA)
Apr 2027Extended by 2 yrs 4 mths
Concrete structure
95%Mid-construction
Booked
7 of 1937%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
6
2 BHK
12
3 BHK
1
Total units
19
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)95%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 90%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 60%Concrete structure (RCC) 95%Excavation 90%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%95%60%7
90%80%0%7
90%80%0%–
90%80%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with up to 40 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 9 mths
Possession date extendedBy 2 yrs 4 mths3 of 5
Possession date (MahaRERA)Apr 2027Jun 2026
Concrete structure (RCC)95%100%
Units booked37%50%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Vasant Prabha by Sudhir Vasant Mayekar is a 19-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in November 2021 with possession due in April 2027. 7 units booked out of total 19 units. The concrete structure (RCC) is 95% complete.

Read full summary

Vasant Prabha is a BMC-sanctioned project by Sudhir Vasant Mayekar in Dadar West, Mumbai 400028, registered with MahaRERA as P51900031637. It was launched in November 2021. It has 19 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 2 years 4 months from the original December 2024. Construction: excavation 90% complete, structure (RCC) 95% complete, final finishes 60% complete.

7 units booked out of total 19 units (37%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 80% to 95% and the possession date has moved from June 2025 to April 2027.