Skip to main content

Zarion, Dadar West

Ready to moveLapsed

by Ayg Homes Constructions Private Limited · Dadar West, Mumbai 400028 · Map

Launched
Nov 20214 yrs 7 mths promised
Possession (MahaRERA)
Jun 2026Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
14 of 1593% · 14 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 15 units

Rehab14 units for existing members

Land-owner share7 units, not for sale

Total 36 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
27
2 BHK
2
Other units
7
Total units
36
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
14
Land-owner share (not for sale)
7
Reserved units
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 88%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 40%Dec 2025: Final finishes 85%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%14
100%100%100%14
100%100%85%12
100%88%40%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400028

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 7 mths3 yrs 6 mths
Possession date extendedNo5 of 6
Possession date (MahaRERA)Jun 2026Dec 2026
Concrete structure (RCC)100%98%
Units booked (free sale)93%46%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Zarion by Ayg Homes Constructions Private Limited is a 36-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in November 2021; its MahaRERA registration has lapsed. 14 units booked out of 15 units for sale. The concrete structure (RCC) is complete.

Read full summary

Zarion is a BMC-sanctioned project by Ayg Homes Constructions Private Limited in Dadar West, Mumbai 400028, registered with MahaRERA as P51900031858. It was launched in November 2021. It has 36 units in 1 building: 29 homes (1 and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 36 units, 15 are for sale, 14 are rehab units for existing members and 7 are the land-owner's share, not for sale.

Possession was due in June 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

14 units booked out of 15 units for sale (93%).