Ajmera Downtown, Kalbadevi

by Ashjit Realties Pvt Ltd · Kalbadevi, Mumbai 400002 · Map

Launched
Nov 20216 yrs 1 mth promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked
73 of 25429% · 60 in Jul 2026
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
72
2 BHK
149
3 BHK
31
Other units
2
Total units
254
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 96%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%73
100%96%0%60
100%50%0%–
100%50%0%27

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ajmera Downtown by Ashjit Realties Pvt Ltd (Ajmera) is a 254-unit BMC-sanctioned project in Kalbadevi, Mumbai 400002, launched in November 2021 with possession due in December 2027. 73 units booked out of total 254 units. The concrete structure (RCC) is complete.

Read full summary

Ajmera Downtown is a BMC-sanctioned project by Ashjit Realties Pvt Ltd in Kalbadevi, Mumbai 400002, registered with MahaRERA as P51900031924. It was launched in November 2021. It has 254 units in 1 building: 252 homes (1, 2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

73 units booked out of total 254 units (29%). Since the July 2026 update, 13 more units have been booked and the reported concrete structure (RCC) has gone from 96% to 100%.

Ajmera's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA23
Total units across these projects4,563
Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all Ajmera projects15 (9 of 23 projects)

See all Ajmera projects →