Suraj Eterna, Mahim
by Suraj Estate Developers Ltd · Mahim, Mumbai 400016 · Map
- Launched
- Dec 20215 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 69 of 69100% · 4 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale69 booked out of 69 units
Rehab4 units for existing members
Total 73 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 53
- 2 BHK
- 18
- Other units
- 2
- Total units
- 73
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 69
- Rehab units
- 4
- Reserved units
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 69 | |
| 100% | 47% | 0% | 69 | |
| 100% | 47% | 0% | – | |
| 100% | 47% | 0% | 43 |
"–" means MahaRERA shows no figure for that update.
About this project
Suraj Eterna by Suraj Estate Developers Ltd is a 73-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in December 2021 with possession due in December 2026. 69 units booked out of 69 units for sale. The concrete structure (RCC) is complete.
Read full summary
Suraj Eterna is a BMC-sanctioned project by Suraj Estate Developers Ltd in Mahim, Mumbai 400016, registered with MahaRERA as P51900032173. It was launched in December 2021. It has 73 units in 1 building: 71 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 73 units, 69 are for sale and 4 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.
69 units booked out of 69 units for sale (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 47% to 100%.
Suraj Estate's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 1,217 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 4 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Suraj Estate projects | 11 (6 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.