- Launched
- Mar 20222 yrs 9 mths originally promised
- Possession (MahaRERA)
- Sep 2025Extended by 9 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 12 of 1486% · 21 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 14 units
Rehab21 units for existing members
Total 35 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 28
- 2 BHK
- 4
- Other units
- 3
- Total units
- 35
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 14
- Rehab units
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 12 | |
| 100% | 100% | 90% | 12 | |
| 100% | 100% | 60% | – | |
| 100% | 100% | 40% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aarush by Konark Enterprises is a 35-unit BMC-sanctioned project in Kalachowki, Mumbai 400033, launched in March 2022; its MahaRERA registration has lapsed. 12 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aarush is a BMC-sanctioned project by Konark Enterprises in Kalachowki, Mumbai 400033, registered with MahaRERA as P51900033696. It was launched in March 2022. It has 35 units in 1 building: 32 homes (1 and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 35 units, 14 are for sale and 21 are rehab units for existing members.
Possession was due in September 2025, after an extension of 9 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
12 units booked out of 14 units for sale (86%).