Lodha NCP, Sion
by Lodha Developers Limited · Sion, Mumbai 400022 · Map
- Launched
- Mar 2022First of 2 phases
- Possession (MahaRERA)
- Jun 2030Extended in 1 of 2 phases
- Concrete structure
- 68%Weighted across 2 phases
- Booked
- 285 of 44564% · 279 in Jul 2026
- Buildings
- 20.5 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 369
- 4 BHK
- 67
- 5+ BHK
- 6
- Other units
- 3
- Total units
- 445
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 2
- MahaRERA complaints
- 2
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Lodha NCP Tower - 1 Completed | P51900034170 | 224 | 100% | 86% | |
| Lodha NCP Tower - 2 Mid-construction | P51900046324 | 218 | 35% | 41% |
Show updates by phase
Lodha NCP Tower - 1 (P51900034170)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 194 | |
| 100% | 100% | 100% | 194 | |
| 100% | 100% | 100% | 193 | |
| 100% | 88% | 15% | 83 |
"–" means MahaRERA shows no figure for that update.
Lodha NCP Tower - 2 (P51900046324)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | 91 | |
| 100% | 15% | 0% | 85 | |
| 100% | 0% | 0% | 41 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Lodha NCP by Lodha Developers Limited is a 445-unit MMRDA-sanctioned project in Sion, Mumbai 400022, registered with MahaRERA in 2 phases, with possession due in June 2030. 285 units booked out of total 445 units. The concrete structure (RCC) is 68% complete.
Read full summary
Lodha NCP is an MMRDA-sanctioned project by Lodha Developers Limited in Sion, Mumbai 400022, registered with MahaRERA as 2 phases (P51900034170, P51900046324). The first phase was launched in March 2022. Together the phases have 445 units in 2 buildings: 442 homes (3, 4 and 5+ BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. On MahaRERA, 1 is completed and 1 is active.
The registered possession date is June 2030; 1 of 2 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 68% complete and final finishes 51% complete. Neither phase has its structure complete.
285 units booked out of total 445 units (64%). Since the July 2026 update, 6 more units have been booked.
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.