Godrej Horizon, Wadala West
by Godrej Projects Development Ltd · Wadala West, Mumbai 400031 · Map
- Launched
- Apr 2022First of 3 phases
- Possession (MahaRERA)
- May 2028 – Jun 2031Not extended
- Concrete structure
- 68%Weighted across 3 phases
- Booked
- 878 of 1,11479% · 814 in Jul 2026
- Buildings
- 64.1 acres
- MahaRERA complaints
- 9Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 16
- 2 BHK
- 633
- 3 BHK
- 463
- 4 BHK
- 2
- Total units
- 1,114
- Buildings
- 6
- Land
- 4.1 acres
- Phases
- 3
- MahaRERA complaints
- 9
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Godrej Horizon Phase I Nearing possession | P51900034851 | 400 | 100% | 98% | |
| Godrej Horizon Phase II Nearing possession | P51900049757 | 352 | 100% | 85% | |
| Godrej Horizon Phase III Early stage | P51900078358 | 362 | 0% | 52% |
Show updates by phase
Godrej Horizon Phase I (P51900034851)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 53% | 390 | |
| 100% | 100% | 20% | 374 | |
| 100% | 100% | 2% | 347 | |
| 100% | 36% | 0% | 319 |
"–" means MahaRERA shows no figure for that update.
Godrej Horizon Phase II (P51900049757)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 10% | 300 | |
| 100% | 91% | 0% | 276 | |
| 100% | 44% | 0% | 259 | |
| 100% | 0% | 0% | 196 |
"–" means MahaRERA shows no figure for that update.
Godrej Horizon Phase III (P51900078358)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 188 | |
| 18% | 0% | 0% | 164 | |
| 18% | 0% | 0% | 133 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Godrej Horizon by Godrej Projects Development Ltd is a 1,114-unit BMC-sanctioned project in Wadala West, Mumbai 400031, registered with MahaRERA in 3 phases, with possession dates from May 2028 to June 2031. 878 units booked out of total 1,114 units. The concrete structure (RCC) is 68% complete.
Read full summary
Godrej Horizon is a BMC-sanctioned project by Godrej Projects Development Ltd in Wadala West, Mumbai 400031, registered with MahaRERA as 3 phases (P51900034851, P51900049757, P51900078358). The first phase was launched in April 2022. Together the phases have 1,114 units in 6 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from May 2028 to June 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 68% complete and final finishes 22% complete. 2 of the 3 phases have their structure complete.
878 units booked out of total 1,114 units (79%). Since the July 2026 update, 64 more units have been booked.
Godrej's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 35 |
|---|---|
| Total units across these projects | 10,289 |
| Completed without extending the possession date | 9 |
| Completed after an extension | 0 |
| Lapsed | 2 |
| Under construction | 24 |
| Possession date extended on the builder's application | 5 |
| Typical time from launch to 100% structure | 6 years 3 months |
| MahaRERA complaints (filed by or against the builder), all Godrej projects | 86 (17 of 35 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.