Lodha Malabar, Malabar Hill

by Lodha Developers Limited · Malabar Hill, Mumbai 400006 · Map

Launched
Apr 20224 yrs 2 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 1 yr
Concrete structure
99%Mid-construction
Booked
25 of 2986% · 24 in Jul 2026
Buildings
21.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

4 BHK
15
5+ BHK
13
Other units
1
Total units
29
Buildings
2
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation99%
Concrete structure (slabs)99%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 88%Dec 2025: Excavation 95%Jul 2026: Excavation 97%Oct 2026: Excavation 99%Dec 2024: Concrete structure (RCC) 6%Dec 2025: Concrete structure (RCC) 45%Jul 2026: Concrete structure (RCC) 89%Oct 2026: Concrete structure (RCC) 99%Dec 2024: Final finishes 39%Dec 2025: Final finishes 0%Jul 2026: Final finishes 20%Oct 2026: Final finishes 75%Excavation 99%Concrete structure (RCC) 99%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
99%99%75%25
97%89%20%24
95%45%0%24
88%6%39%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Lodha Malabar by Lodha Developers Limited is a 29-unit BMC-sanctioned project in Malabar Hill, Mumbai 400006, launched in April 2022 with possession due in June 2027. 25 units booked out of total 29 units. The concrete structure (RCC) is 99% complete.

Read full summary

Lodha Malabar is a BMC-sanctioned project by Lodha Developers Limited in Malabar Hill, Mumbai 400006, registered with MahaRERA as P51900034949. It was launched in April 2022. It has 29 units in 2 buildings: 28 homes (4 and 5+ BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 1 year from the original June 2026. Construction: excavation 99% complete, structure (RCC) 99% complete, final finishes 75% complete.

25 units booked out of total 29 units (86%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 89% to 99%.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →