- Launched
- May 20222 yrs 11 mths originally promised
- Possession (MahaRERA)
- Mar 2026Extended by 11 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 2 of 1811% · 7 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 18 units
Rehab7 units for existing members
Total 25 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 25
- Total units
- 25
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 2 | |
| 100% | 100% | 95% | 2 | |
| 100% | 100% | 50% | 2 | |
| 100% | 85% | 15% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Belvedere by J K Estates is a 25-unit BMC-sanctioned project in Sion, Mumbai 400022, launched in May 2022; its MahaRERA registration has lapsed. 2 units booked out of 18 units for sale. The concrete structure (RCC) is complete.
Read full summary
Belvedere is a BMC-sanctioned project by J K Estates in Sion, Mumbai 400022, registered with MahaRERA as P51900045245. It was launched in May 2022. It has 25 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 25 units, 18 are for sale and 7 are rehab units for existing members.
Possession was due in March 2026, after an extension of 11 months from the original April 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
2 units booked out of 18 units for sale (11%).