Shree Mahalakshmi Residency, Mahim
Lapsed
by Shree Mahalakshmi Constructions · Mahim, Mumbai 400016 · Map
- Launched
- May 20223 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 11 of 2446%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 15
- 2 BHK
- 8
- Other units
- 1
- Total units
- 24
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 11 | |
| 100% | 100% | 50% | 11 | |
| 100% | 100% | 50% | 11 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Shree Mahalakshmi Residency by Shree Mahalakshmi Constructions is a 24-unit BMC-sanctioned project in Mahim, Mumbai 400016, launched in May 2022; its MahaRERA registration has lapsed. 11 units booked out of total 24 units. The concrete structure (RCC) is complete.
Read full summary
Shree Mahalakshmi Residency is a BMC-sanctioned project by Shree Mahalakshmi Constructions in Mahim, Mumbai 400016, registered with MahaRERA as P51900045601. It was launched in May 2022. It has 24 units in 1 building: 23 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 1 year from the original June 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
11 units booked out of total 24 units (46%).