Bellevue Tower - 3, Mahalaxmi

by Lodha Developers Limited · Mahalaxmi, Mumbai 400011 · Map

Launched
Aug 20225 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked
172 of 23174% · 160 in Jul 2026
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

3 BHK
177
4 BHK
53
Other units
1
Total units
231
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 40%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%172
100%100%40%160
100%100%10%85
100%50%0%58

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Bellevue Tower - 3 by Lodha Developers Limited is a 231-unit BMC-sanctioned project in Mahalaxmi, Mumbai 400011, launched in August 2022 with possession due in December 2027. 172 units booked out of total 231 units. The concrete structure (RCC) is complete.

Read full summary

Bellevue Tower - 3 is a BMC-sanctioned project by Lodha Developers Limited in Mahalaxmi, Mumbai 400011, registered with MahaRERA as P51900046594. It was launched in August 2022. It has 231 units in 1 building: 230 homes (3 and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

172 units booked out of total 231 units (74%). Since the July 2026 update, 12 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)

See all Lodha projects →