Chirag Heights, Dadar East
by Nettheim Builders LLP · Dadar East, Mumbai 400014 · Map
- Launched
- Oct 20223 yrs 2 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 5 of 2322% · 10 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 23 units
Rehab10 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 23
- 3 BHK
- 9
- Other units
- 1
- Total units
- 33
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 23
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 32% | 5 | |
| 100% | 100% | 32% | 7 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400014
Projects with 10–70 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 2 mths | 3 yrs 8 mths |
| Possession date extended | By 1 yr | 0 of 3 |
| Possession date (MahaRERA) | Dec 2026 | Dec 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked (free sale) | 22% | 62% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 3 projects
- Bhalchandra Niwas Chs, Dadar East
- Yash Supriya, Dadar East
- Pole Star, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bhalchandra Niwas Chs | April 2023 | December 2026 | 100% | 15 units booked out of total 24 units |
| Yash Supriya | May 2023 | December 2026 | 95% | 6 units booked out of 13 units for sale |
| Pole Star | June 2023 | December 2027 | 100% | 34 units booked out of total 38 units |
About this project
Chirag Heights by Nettheim Builders LLP is a 33-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in October 2022 with possession due in December 2026. 5 units booked out of 23 units for sale. The concrete structure (RCC) is complete.
Read full summary
Chirag Heights is a BMC-sanctioned project by Nettheim Builders LLP in Dadar East, Mumbai 400014, registered with MahaRERA as P51900047318. It was launched in October 2022. It has 33 units in 1 building: 32 homes (2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 23 are for sale and 10 are rehab units for existing members.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 32% complete.
5 units booked out of 23 units for sale (22%).