Yash Supriya, Dadar East
by Yash Construction Company · Dadar East, Mumbai 400014 · Map
- Launched
- May 20233 yrs 7 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 6 of 1346% · 16 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 13 units
Rehab16 units for existing members
Total 29 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 1
- 2 BHK
- 27
- Other units
- 1
- Total units
- 29
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 13
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 6 | |
| 100% | 95% | 0% | 4 | |
| 100% | 30% | 0% | 3 | |
| 100% | 30% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400014
Projects with 10–60 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 7 mths | 4 yrs 1 mth |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Dec 2026 | Jun 2027 |
| Concrete structure (RCC) | 95% | 100% |
| Units booked (free sale) | 46% | 46% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Bhalchandra Niwas Chs, Dadar East
- Pole Star, Dadar East
- Chirag Heights, Dadar East
- Ram Setu Bhavan, Dadar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bhalchandra Niwas Chs | April 2023 | December 2026 | 100% | 15 units booked out of total 24 units |
| Pole Star | June 2023 | December 2027 | 100% | 34 units booked out of total 38 units |
| Chirag Heights | October 2022 | December 2026 | 100% | 5 units booked out of 23 units for sale |
| Ram Setu Bhavan | March 2024 | December 2028 | 90% | 7 units booked out of 24 units for sale |
About this project
Yash Supriya by Yash Construction Company is a 29-unit BMC-sanctioned project in Dadar East, Mumbai 400014, launched in May 2023 with possession due in December 2026. 6 units booked out of 13 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Yash Supriya is a BMC-sanctioned project by Yash Construction Company in Dadar East, Mumbai 400014, registered with MahaRERA as P51900050949. It was launched in May 2023. It has 29 units in 1 building: 28 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 13 are for sale and 16 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
6 units booked out of 13 units for sale (46%). Since the July 2026 update, 2 more units have been booked.