Suraj Park View, Dadar West
by Suraj Estate Developers Ltd · Dadar West, Mumbai 400028 · Map
- Launched
- Dec 2022First of 2 phases
- Possession (MahaRERA)
- Dec 2026 – Dec 2031Not extended
- Concrete structure
- 42%Weighted across 2 phases
- Booked (free sale)
- 65 of 8973% · 83 rehab units
- Buildings
- 20.6 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale65 booked out of 89 units
Rehab83 units for existing members
Total 172 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 88
- 2 BHK
- 80
- 3 BHK
- 2
- 4 BHK
- 2
- Total units
- 172
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 2
- MahaRERA complaints
- 1
- Free-sale units
- 89
- Rehab units
- 83
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Suraj Park View 2 Nearing possession | P51900047891 | 72 | 100% | 54% | |
| Suraj Park View 1 Early stage | PR1170002500887 | 100 | 0% | 26% |
Show updates by phase
Suraj Park View 2 (P51900047891)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 39 | |
| 100% | 0% | 0% | 38 | |
| 100% | 0% | 0% | 37 | |
| 100% | 0% | 0% | 32 |
"–" means MahaRERA shows no figure for that update.
Suraj Park View 1 (PR1170002500887)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 5% | 0% | 0% | 26 | |
| 0% | 0% | 0% | 21 | |
| 0% | 0% | 0% | 9 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Suraj Park View by Suraj Estate Developers Ltd is a 172-unit BMC-sanctioned project in Dadar West, Mumbai 400028, registered with MahaRERA in 2 phases, with possession dates from December 2026 to December 2031. 65 units booked out of 89 units for sale. The concrete structure (RCC) is 42% complete.
Read full summary
Suraj Park View is a BMC-sanctioned project by Suraj Estate Developers Ltd in Dadar West, Mumbai 400028, registered with MahaRERA as 2 phases (P51900047891, PR1170002500887). The first phase was launched in December 2022. Together the phases have 172 units in 2 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA. Of the 172 units, 89 are for sale and 83 are rehab units for existing members.
The phases' registered possession dates run from December 2026 to December 2031; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 42% complete and final finishes 0% complete. Neither phase has its structure complete.
65 units booked out of 89 units for sale (73%). Since the July 2026 update, 6 more units have been booked.
Suraj Estate's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 1,217 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 4 |
| Lapsed | 3 |
| Under construction | 10 |
| Possession date extended on the builder's application | 10 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Suraj Estate projects | 11 (6 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.