Sidheshwar Royale, Chembur
by M/S Yug Developers · Chembur, Mumbai 400071 · Map
- Launched
- Dec 20223 yrs 3 mths originally promised
- Possession (MahaRERA)
- Jul 2027Extended by 1 yr 4 mths
- Concrete structure
- 95%Mid-construction
- Booked (free sale)
- 9 of 2241% · 3 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale9 booked out of 22 units
Rehab3 units for existing members
Land-owner share22 units, not for sale
Total 47 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 5
- 2 BHK
- 6
- 3 BHK
- 26
- 4 BHK
- 2
- Other units
- 8
- Total units
- 47
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 3
- Land-owner share (not for sale)
- 22
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 60% | 9 | |
| 100% | 95% | 30% | 9 | |
| 100% | 70% | 0% | – | |
| 100% | 70% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400071
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 2 mths |
| Possession date extended | By 1 yr 4 mths | 4 of 6 |
| Possession date (MahaRERA) | Jul 2027 | Dec 2026 |
| Concrete structure (RCC) | 95% | 95% |
| Units booked (free sale) | 41% | 67% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Radha Continental, Chembur
- Arham Arya, Chembur
- Tigon Elite, Chembur
- Arham Aryan, Chembur
- Nirvaana Solitaire, Chembur
- Janki Heritage, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Radha Continental | February 2023 | October 2027 | 90% | 7 units booked out of 10 units for sale |
| Arham Arya | February 2023 | December 2026 | 100% | 46 units booked out of 48 units for sale |
| Tigon Elite | October 2022 | December 2026 | 100% | 75 units booked out of 76 units for sale |
| Arham Aryan | May 2023 | December 2026 | 50% | 11 units booked out of 17 units for sale |
| Nirvaana Solitaire | June 2022 | December 2026 | 40% | 10 units booked out of 22 units for sale |
| Janki Heritage | June 2022 | December 2025 | 100% | 17 units booked out of 42 units for sale |
About this project
Sidheshwar Royale by M/S Yug Developers is a 47-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in December 2022 with possession due in July 2027. 9 units booked out of 22 units for sale. The concrete structure (RCC) is 95% complete.
Read full summary
Sidheshwar Royale is a BMC-sanctioned project by M/S Yug Developers in Chembur, Mumbai 400071, registered with MahaRERA as P51900047936. It was launched in December 2022. It has 47 units in 1 building: 39 homes (1 RK, 2 BHK, 3 BHK and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 47 units, 22 are for sale, 3 are rehab units for existing members and 22 are the land-owner's share, not for sale.
Its registered possession date is July 2027, extended by 1 year 4 months from the original March 2026. Construction: excavation complete, structure (RCC) 95% complete, final finishes 60% complete.
9 units booked out of 22 units for sale (41%).