Radha Continental, Chembur
by Sacvir Dimensions LLP · Chembur, Mumbai 400071 · Map
- Launched
- Feb 20234 yrs 8 mths promised
- Possession (MahaRERA)
- Oct 2027Not extended
- Concrete structure
- 90%Mid-construction
- Booked (free sale)
- 7 of 1070%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 10 units
Land-owner share11 units, not for sale
Total 21 units. Land-owner units are not for sale.
Project facts
- 4 BHK
- 21
- Total units
- 21
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Land-owner share (not for sale)
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 0% | 7 | |
| 0% | 0% | 0% | 7 | |
| 0% | 0% | 0% | 7 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400071
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 2 yrs 6 mths |
| Possession date extended | No | 4 of 4 |
| Possession date (MahaRERA) | Oct 2027 | Dec 2026 |
| Concrete structure (RCC) | 90% | 92% |
| Units booked (free sale) | 70% | 48% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Heritage Signature, Chembur
- Sidheshwar Royale, Chembur
- Arham Aryan, Chembur
- Ambal Parijath Chsl, Chembur
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Heritage Signature | February 2023 | March 2026 | 100% | 3 units booked out of total 11 units |
| Sidheshwar Royale | December 2022 | July 2027 | 95% | 9 units booked out of 22 units for sale |
| Arham Aryan | May 2023 | December 2026 | 50% | 11 units booked out of 17 units for sale |
| Ambal Parijath Chsl | June 2023 | December 2026 | 90% | 5 units booked out of 9 units for sale |
About this project
Radha Continental by Sacvir Dimensions LLP is a 21-unit BMC-sanctioned project in Chembur, Mumbai 400071, launched in February 2023 with possession due in October 2027. 7 units booked out of 10 units for sale. The concrete structure (RCC) is 90% complete.
Read full summary
Radha Continental is a BMC-sanctioned project by Sacvir Dimensions LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800049683. It was launched in February 2023. It has 21 units in 1 building, with 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 10 are for sale and 11 are the land-owner's share, not for sale.
Its registered possession date is October 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.
7 units booked out of 10 units for sale (70%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 90%.