Saraswati Niwas, Dadar West
Ready to moveLapsed
by Sugee Twenty Three Developers LLP · Dadar West, Mumbai 400028 · Map
- Launched
- Dec 20223 yrs 4 mths promised
- Possession (MahaRERA)
- Apr 2026Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 11 of 11100%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 3
- 3 BHK
- 7
- Other units
- 1
- Total units
- 11
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 11 | |
| 100% | 100% | 100% | 11 | |
| 100% | 100% | 40% | – | |
| 100% | 86% | 0% | 8 |
"–" means MahaRERA shows no figure for that update.
About this project
Saraswati Niwas by Sugee Twenty Three Developers LLP is an 11-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in December 2022; its MahaRERA registration has lapsed. 11 units booked out of total 11 units. The concrete structure (RCC) is complete.
Read full summary
Saraswati Niwas is a BMC-sanctioned project by Sugee Twenty Three Developers LLP in Dadar West, Mumbai 400028, registered with MahaRERA as P51900048130. It was launched in December 2022. It has 11 units in 1 building: 10 homes (1 RK and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in April 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
11 units booked out of total 11 units (100%).