Skip to main content

Darul Mustafa, Mazgaon

Ready to move

by Citymaker Builders Private Limited · Mazgaon, Mumbai 400010 · Map

Launched
Jan 20234 yrs 11 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Ready to move
Booked (free sale)
9 of 3030% · 42 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale9 booked out of 30 units

Rehab42 units for existing members

Total 72 units. Rehab units are not for sale.

Project facts

1 BHK
51
2 BHK
16
3 BHK
1
Other units
4
Total units
72
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
42

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 50%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%9
100%100%100%9
100%100%50%6
100%75%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400010

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400010
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths4 yrs 4 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2027Jul 2027
Concrete structure (RCC)100%64%
Units booked (free sale)30%56%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Darul Mustafa by Citymaker Builders Private Limited is a 72-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in January 2023 with possession due in December 2027. 9 units booked out of 30 units for sale. The concrete structure (RCC) is complete.

Read full summary

Darul Mustafa is a BMC-sanctioned project by Citymaker Builders Private Limited in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900048664. It was launched in January 2023. It has 72 units in 1 building: 68 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 72 units, 30 are for sale and 42 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

9 units booked out of 30 units for sale (30%).