Azara Residences, Mazgaon
by Azara Redstone LLP · Mazgaon, Mumbai 400010 · Map
- Launched
- Feb 20234 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 29%Mid-construction
- Booked
- 30 of 8038% · 15 in Jul 2026
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 20
- 2 BHK
- 40
- 3 BHK
- 20
- Total units
- 80
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 29% | 0% | 30 | |
| 100% | 3% | 0% | 15 | |
| 100% | 0% | 0% | 15 | |
| 100% | 0% | 0% | 9 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400010
Projects with 40–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 10 mths | 4 yrs 4 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2027 | Jul 2027 |
| Concrete structure (RCC) | 29% | 100% |
| Units booked | 38% | 52% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Darul Mustafa, Mazgaon
- Bayview Phase-II, Mazgaon
- Deja View, Mazgaon
- Ganga Avenue, Mazgaon
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Darul Mustafa | January 2023 | December 2027 | 100% | 9 units booked out of 30 units for sale |
| Bayview Phase-II | January 2023 | December 2027 | 100% | 46 units booked out of total 60 units |
| Deja View | June 2023 | March 2027 | 0% | 0 units booked out of 29 units for sale |
| Ganga Avenue | August 2022 | December 2025 | 100% | 36 units booked out of total 48 units |
About this project
Azara Residences by Azara Redstone LLP is an 80-unit BMC-sanctioned project in Mazgaon, Mumbai 400010, launched in February 2023 with possession due in December 2027. 30 units booked out of total 80 units. The concrete structure (RCC) is 29% complete.
Read full summary
Azara Residences is a BMC-sanctioned project by Azara Redstone LLP in Mazgaon, Mumbai 400010, registered with MahaRERA as P51900049639. It was launched in February 2023. It has 80 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 29% complete, final finishes not started.
30 units booked out of total 80 units (38%). Since the July 2026 update, 15 more units have been booked and the reported concrete structure (RCC) has gone from 3% to 29%.