Bellissimo Matunga, Sion

by Lodha Developers Limited · Sion, Mumbai 400022 · Map

Launched
Feb 2023First of 4 phases
Possession (MahaRERA)
Dec 2027 – Mar 2030Not extended
Concrete structure
56%Weighted across 4 phases
Booked
486 of 66473% · 465 in Jul 2026
Buildings
52.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
4
2 BHK
278
3 BHK
280
4 BHK
75
5+ BHK
7
Other units
20
Total units
664
Buildings
5
Land
2.6 acres
Phases
4
MahaRERA complaints
0

The 4 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Bellissimo Matunga
Nearing possession
P51900049433145100%96%
Bellissimo Matunga-Tower 2
Nearing possession
P51900051742111100%88%
Bellissimo Matunga-Tower 3
Nearing possession
P51900051743103100%91%
Bellissimo Matunga -Tower 4 and Tower 5
Early stage
P519000785022850%49%
Show updates by phase

Bellissimo Matunga (P51900049433)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%142
100%100%40%140
100%100%40%132
100%72%0%111

"–" means MahaRERA shows no figure for that update.

Bellissimo Matunga-Tower 2 (P51900051742)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%102
100%100%28%101
100%100%22%97
100%28%0%66

"–" means MahaRERA shows no figure for that update.

Bellissimo Matunga-Tower 3 (P51900051743)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%35%97
100%100%22%95
100%100%22%91
100%46%0%71

"–" means MahaRERA shows no figure for that update.

Bellissimo Matunga -Tower 4 and Tower 5 (P51900078502)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%145
0%0%0%129
0%0%0%94
0%0%0%0

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation56%
Concrete structure (slabs)56%
Finishes, lifts and services22%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 56%Dec 2025: Excavation 56%Jul 2026: Excavation 56%Oct 2026: Excavation 56%Dec 2024: Concrete structure (RCC) 28%Dec 2025: Concrete structure (RCC) 56%Jul 2026: Concrete structure (RCC) 56%Oct 2026: Concrete structure (RCC) 56%Dec 2024: Final finishes 0%Dec 2025: Final finishes 16%Jul 2026: Final finishes 17%Oct 2026: Final finishes 22%Excavation 56%Concrete structure (RCC) 56%Final finishes 22%

How to read construction stages

About this project

Bellissimo Matunga by Lodha Developers Limited is a 664-unit project in Sion, Mumbai 400022, registered with MahaRERA in 4 phases, with possession dates from December 2027 to March 2030. 486 units booked out of total 664 units. The concrete structure (RCC) is 56% complete.

Read full summary

Bellissimo Matunga is a project by Lodha Developers Limited in Sion, Mumbai 400022, registered with MahaRERA as 4 phases (P51900049433, P51900051742, P51900051743, P51900078502). The first phase was launched in February 2023. Together the phases have 664 units in 5 buildings: 644 homes (1, 2, 3, 4 and 5+ BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. All 4 phases are active on MahaRERA.

The phases' registered possession dates run from December 2027 to March 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 56% complete and final finishes 22% complete. 3 of the 4 phases have their structure complete.

486 units booked out of total 664 units (73%). Since the July 2026 update, 21 more units have been booked.

Lodha's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA85
Total units across these projects15,101
Completed without extending the possession date31
Completed after an extension13
Lapsed0
Under construction41
Possession date extended on the builder's application34
Typical time from launch to 100% structure5 years 10 months
MahaRERA complaints (filed by or against the builder), all Lodha projects242 (38 of 85 projects)